Call for Kildare County Council to speed up launch and promotion of ambitious project
By Ciarán Mather · Leinster Leader · 20 November 2026

KCC also asserted that an upcoming meeting will address concerns raised about the project
By Ciarán Mather Published 20th Nov 2026, 12:30 GMT The project was highlighted at a recent Kildare County Council meeting. Pictured above is Áras Chill Dara, which is the official headquarters of Kildare County Council, in the Devoy Park area of Naas | FILE PHOTOGRAPH KCC also asserted that an upcoming meeting will address concerns raised about the project Kildare County Council (KCC) has been urged to speed up the launch and promotion of one ambitious project.
The appeal was made by Fine Gael councillor Kevin Duffy at the latest Kildare-Newbridge Municipal District meeting, and related to the Barrow Blueway project.
Read More Minister welcomes Men’s Shed funding for North Kildare Kildare playground ‘expected to be substantially complete’ soon Kildare Garda convicted of murder is subject of podcast Delay in reporting separation of UN convoy before fatal shooting, inquest told Kildare man in court for fighting with his father in broad daylight Driver fined for striking a pedestrian who ignored a red light on Kildare street Sign up to our Kildare Live newsletter Sign up Thank you for signing up! Did you know you can manage your profile, and explore all of the available newsletters from Kildare Live within your account.
During this meeting, which took place on Wednesday, November 18 last, he raised the subject when motioned for KCC to ‘make a commitment to achieving the Blueway Accreditation for the Barrow Blueway project on completion of the pedestrian bridge at Spencer Bridge in Rathangan , to enable the official launch and promotion of the Blueway to occur in Spring / Summer 2027’.
His motion was seconded by his party colleague, Cllr Tracey O’Dwyer.
Cllr Kevin Duffy (Fine Gael) | PHOTOGRAPH CREDIT: KILDARECOCO.IE In response to Cllr Duffy’s motion, KCC had this to say: “Members may be aware that the project is funded through Rural Regeneration and Development Fund grant funding, with two applications for funding having been successfully awarded, the second in May 2024.
“As with all capital projects, rising inflation has had a significant impact on the budget.
“ In setting out a project programme, every effort is made to ensure that it is achieved within the shortest timeframe possible”.
However, KCC also revealed: “Delays were incurred during the process, some of which were outside the control of the contractor and the local authorities.
Moreover, KCC noted that The Steering Group, which is made up of Kildare County Council , Laois County Council and Waterways Ireland, is due to meet in the coming weeks, and assured councillors that the ‘concerns’ from the Monasterevin Barrow Blueway Committee ‘will be discussed’ at this meeting.
“The Strategic Projects and Public Realm department team will be able to issue a further update after that meeting has taken place,” KCC added.
Reporting by Ciarán Mather for Leinster Leader, funded by the Local Democracy Reporting Scheme. Republished by News Room under the scheme’s reuse permission.